BOM Studio · Logistics

Packing & Shipping Documents: Every Package Accounted For

Export packing decides what your site receives. In BOM Studio, only members released by QC can be packed, every package is scanned into its container, every load plan is checked, and the released packing list is locked. You receive professional documents and a QR code on every package, so your team can check each container on arrival.

Tay Ninh, Vietnam Engineering · Fabrication · Shipping Destination: Guyana

Screens

Packing and shipping in BOM Studio

Container load plan with erection priority

Container load plans checked before loading

Packages are placed on plan and elevation views and checked in 3D for collisions, door clearance, roof clearance, payload, centre of gravity and stacking. Packages needed first on site are placed near the door.

  • Several options, with revisions
  • Locked once approved
  • VALIDATED / WARNING / NOT VERIFIED

From released member to site receiving

Each step is checked by the system and recorded.

  1. 01

    Eligible members only

    Only members that are finished, released by QC, painted and free of open NCRs can be added to a packing list. Each member is controlled by serial number and can never be packed twice.

    Related documents: Eligibility check

  2. 02

    Scan into packages

    Packers scan, check, confirm and save. The system flags a wrong package, a wrong container, an ineligible member or one already packed elsewhere. A scan is never a QC pass.

    Related documents: Package (Sub-PKL) with QR label

  3. 03

    Packed in erection order

    Packing follows the erection zones and sequence, so the first members your crew needs arrive together.

    Related documents: Container to erection zone

  4. 04

    Load plan

    Containers are loaded to a checked plan. Container numbers are validated to ISO 6346.

    Related documents: Approved load plan

  5. 05

    Check and seal

    A supervisor checks the packages and the container, and the seal number is entered twice.

    Related documents: Seal record, packing photographs

  6. 06

    Release

    The final packing list is released as a locked snapshot with a SHA-256 hash. Any later change needs an amendment with a reason and approval.

    Related documents: Released packing list (PDF and Excel)

  7. 07

    Handover to the carrier

    A ten-point checklist checked against the system data, signed by our supervisor and logistics team and by the driver on screen.

    Related documents: Container handover certificate

  8. 08

    Your documents

    Client packing list, shipping marks and the container packing report, by QR code, share link with PIN or client account.

    Related documents: Client document set

  9. 09

    Site receiving

    Your site team checks the seal on arrival and scans each package, recording damage or shortages with photographs. Nothing is received automatically.

    Related documents: Receiving record

What each container packing report covers

One report per container, for your team on site and your customs broker.

SectionContentsReference
ContainerContainer number and size-type code, CSC plate, condition timelineISO 6346
ShippingShipping line, booking, B/L, vessel, ports of loading and discharge, ETD / ETA, cut-off
WeightVerified gross mass of the packed containerSOLAS Chapter VI, Regulation 2
InspectionSeven-point container inspection and seven condition points before loadingC-TPAT / WCO SAFE
SecuringPacking and securing, timber dunnageCTU Code, ISPM 15
SealSeal number and classISO 17712
Photographs and videoLoading photographs in work order, with time taken and SHA-256; loading video viewable on a phone
DocumentsInvoice, B/L, certificate of origin, EN 10204 3.1 mill certificates, coating records, ISPM 15, with their status
UnloadingUnloading order, receiving checklist and confirmation

Container data such as tare and maximum gross are typical values until confirmed against the CSC plate. The person who signs the VGM is responsible for it.

Client Documents

Documents in your language, with nothing internal

Client packing lists, shipping marks and container packing reports can be issued in 19 languages, or bilingual with English. International codes, steel designations, piece marks and figures are never translated. A machine translation is reviewed and approved before it reaches you; until then it is marked as not reviewed and cannot be shared by link or QR code.

Documents for clients only contain released data and published photographs, video and documents. User names, warehouse locations, internal QC or NCR notes and prices are never shown.

Ways to receive them

  • QR code on the shipping mark or report
  • Share link with an expiry date and a PIN
  • Client account showing released documents only
  • PDF and Excel files

Performed directly by World Steel

FAQ

Packing and documents: questions

Straight answers on scope, design codes, shipping and what happens in Guyana.

Ask an engineer
How do I check that everything was loaded?

Scan the QR code on each package or use the client packing list. The container packing report shows the packing list, the seal number and the photographs and video of the loading.

Can the packing list change after shipment?

Not silently. The released packing list is locked with a SHA-256 hash. Any later change needs an amendment with a reason and an approval, and it is recorded.

Are the load plans a lashing certificate?

No. Load plans support planning and are checked for clearances, payload and centre of gravity, but they are not a certificate of safe securing.

Which delivery terms do you ship under?

FOB, CFR or CIF to the port of Georgetown. Customs clearance, port handling and inland transport in Guyana are arranged by the client or licensed local partners.

Plan Your Shipment with Us

Tell us about your project and your preferred delivery terms. We will show you how it would be packed, loaded and documented.

Your details
Your building
Incoterms for your quotation

Choose the delivery terms you would like us to quote (Incoterms® 2020). You can select more than one to compare.

Scope of supply

Stamped structural design for permit purposes and construction/erection in Guyana are not included by default. They are arranged with a locally registered engineer and contractor where required.

Project information

We usually respond within two business days (Vietnam time, GMT+7). Your information is never sold or shared for marketing by third parties.

More from BOM Studio

BOM Studio: World Steel Technology

World Steel's own project platform. Every steel member has an ID and QR code, and every step from production to handover is recorded, so you can follow your pr…

Read more

Real-Time Production Reports

Follow the fabrication of your building live: progress by steel weight for every stage, a coloured 3D model, factory photographs and weekly reports from a secu…

Read more

Real-Time Quality Control

Every inspection recorded as it happens: hold points, PASS / FAIL by a QC inspector, NCRs tracked to closure, welder qualifications checked by the system and f…

Read more

Smart Erection

Traceability that continues on site: component passports by QR code, model navigation, erection sequence, 4D progress, site inspections and an offline site app…

Read more

Digital Handover

A complete, verifiable record of your building, generated from the project data and locked with a SHA-256 manifest.

Read more

Project Risk Control

The risks of an overseas steel project, from model errors to missing members on site, and how BOM Studio controls each one with a check, a rule and a record.

Read more

Export Process & Packing Control

Every member inspected, marked, listed, packed, loaded and photographed: how World Steel makes sure your project in Guyana receives exactly what was designed, …

Read more

Shipping Lines & Transit Times: Vietnam to Guyana

The international shipping lines, routes and transshipment hubs that connect Vietnam with Georgetown, the weekly sailing rhythm, a realistic 45–60 day transit …

Read more

Engineering Solutions

Structural engineering coordination, design optimization, connection detailing, shop drawings, BIM coordination and technical documentation.

Read more